Xinhai Sudan 300 TPD Gold Plant- Xinhai
Xinhai Sudan 300 TPD Gold Plant Xinhai Sudan 300 TPD gold plant has been completed equipment installation process, let us look at its Project Site. Screening Screening Grinding and Classification Grinding and Classification The raw ore is gold tailings with small particle size, so Xinhai used one stage closed-circuit grinding and classification process. Belt conveyor transported the ore to the ball mill, the discharge of ball mill was sent to hydro cyclone unit for classification with slurry pump, settled sand of hydro cyclone unit returned to ball mill for re-grinding through automatic flow, the overflow entered into the next process through automatic flow. Cyaniding Extraction of Gold Cyaniding Extraction of Gold Cyanide leaching adopted 7 double impeller efficient agitation leaching tanks, one of them is a pre-leaching tank, six tanks were leaching tanks, activated carbon adsorbed gold, after full adsorption, gold loaded carbon was separated f...